Massena Central School District moving ahead with phase three of capital project | Education | nny360.com

2022-03-24 11:20:44 By : Ms. Marisa Shen

Please purchase a subscription to read our premium content. If you have a subscription, please log in or sign up for an account on our website to continue.

Please log in, or sign up for a new account to continue reading.

Thank you for using NNY360! We hope that you continue to enjoy our free content.

Welcome! We hope that you enjoy our complimentary NNY360 content.

Thank you for using NNY360! Support local journalism — join now!

Thank you for using NNY360! Support local journalism — join now!

Thank you for signing in! We hope that you continue to enjoy our free content.

Thank you for using NNY360! We hope that you continue to enjoy our complimentary NNY360 content.

Thank you for using NNY360! We hope that you continue to enjoy our complimentary NNY360 content.

Thank you for using NNY360! We hope that you continue to enjoy our complimentary NNY360 content.

Thank you for using NNY360! We hope that you continue to enjoy our complimentary NNY360 content.

Thank you for using NNY360! We hope that you continue to enjoy our complimentary NNY360 content.

Checking back? Since you viewed this item previously you can read it again. To enjoy all our content, join now!

Log in or sign up for a new account and join now to continue reading.

Join now to continue reading.

Your current subscription does not provide access to this content.

Sorry, no promotional deals were found matching that code.

Promotional Rates were found for your code.

Rain showers this morning with mostly cloudy conditions during the afternoon hours. High near 55F. Winds S at 10 to 20 mph. Chance of rain 60%..

Considerable cloudiness with occasional rain showers. Low near 40F. Winds S at 5 to 10 mph. Chance of rain 60%.

Phase three work of the Massena Central School District’s $49.6 million capital project is on track to begin in June after rebids for the project came within budget and were approved by the district’s board of education last week. Christopher Lenney/Watertown Daily Times

Phase three work of the Massena Central School District’s $49.6 million capital project is on track to begin in June after rebids for the project came within budget and were approved by the district’s board of education last week. Christopher Lenney/Watertown Daily Times

MASSENA — Phase-three work for the Massena Central School District’s $49.6 million capital project is on track to begin in June after rebids for the project came within budget and were approved by the district’s board of education last week.

The board had rejected the initial bids. The district had $8.6 remaining for phase-three work, but bids came in at $12.1 million. That figure doesn’t count upgrades to the emergency notification system at the high school and junior high, which were already in the budget.

“This was a rebid as the bids that came in from contractors on Jan. 25 were over our budget. This led to a paring down of this final phase of the project,” Superintendent Patrick H. Brady said.

After a successful opening of rebids, general construction work was awarded to Bette & Cring, Watertown; mechanical construction work was awarded to Northern Mechanicals Inc., Norwood; electrical construction work was awarded to Dow Electric Inc., Malone; plumbing construction work was awarded to Norwood Plumbing Inc.; asbestos abatement was awarded to NRC East Environmental Services Inc., Syracuse; food service construction work was awarded to Second & Broad Street Sales Corp., Utica, doing business as Joseph Flihan Co.; and theatrical systems construction work was awarded to Janson Industries, Ohio.

Edward Bernhauer, an architect with the IBI Group, the district’s architectural firm, told board members last month that the scope of phase-three work was reduced “to realign with budget at current market costs.” After some modifications were made to the scope of the project, it was put out for bid again.

Twenty-one items were removed from the scope of the project at the high school, while 15 items were removed at the junior high school, four items were removed from the Central Administration Building and three items were removed from the Shared Transportation Facility.

Among the removed high school items were wrestling area renovations, auditorium HVAC system renovation; heat in the coach’s office and ventilation in the boys’ locker room; girls’ locker room and office renovation; team room renovation adjacent to the girls’ locker room; nurses’s office renovation; kitchen equipment renovations; and exterior door replacement at select locations.

Also included at the high school were auditorium aisle lighting; music suite renovation; a district digital marquee sign; mechanical system renovations; classroom ceiling replacement; additional kitchen equipment; additional kitchen electrical renovations; water heater replacement; electrical service renovations; electrical service site renovations; and new boiler room.

At the junior high school, deleted items are exterior door replacement; ceiling replacement; classroom lighting replacement; asbestos abatement; locker replacement; flooring replacement; carpet flooring replacement; dust collector relocation; electric service renovations; electric service site renovations; an additional gender neutral toilet room; special education room renovation; exterior masonry renovation; gym floor refinishing; and an additional sidewalk to connect to a future village sidewalk.

The four removed items in the Central Administration Building were boiler room modifications for the high school and Central Administration Building; boiler room electrical modifications; and generator connection modifications.

At the Shared Transportation Facility, deleted items are air handler unit, gas-fired unit heater replacement and fire alarm system replacement.

Construction is scheduled to begin in June and run through fall 2023 and is largely focused on the junior high and high school.

Email notifications are only sent once a day, and only if there are new matching items.

Your comment has been submitted.

There was a problem reporting this.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language. PLEASE TURN OFF YOUR CAPS LOCK. Don't Threaten. Threats of harming another person will not be tolerated. Be Truthful. Don't knowingly lie about anyone or anything. Be Nice. No racism, sexism or any sort of -ism that is degrading to another person. Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts. Share with Us. We'd love to hear eyewitness accounts, the history behind an article.

Get the most of NNY360, register today!

By providing your email address, you consent to receive emails and special offers from NNY360.com

Get Breaking News Alerts deliverd FREE to your inbox

Success! An email has been sent to with a link to confirm list signup.

Error! There was an error processing your request.

By providing your email address, you consent to receive emails and special offers from NNY360.com